News from Network Rail
Green Lane Miniature Stop Lights
Network Rail have advised us that by means of an update to the current situation please find below plan for the lead in to the commissioning of the new MSL system at Green Lane.
Monday night 2nd June to Thursday night 5th June: 23:00 – 05:00, construction of the MSL and some testing. There may be some noise, but it will be kept to a minimum.
Monday night 23rd June to Thursday night 26th June: 23:00 – 05:00, testing of the MSL system which may generate some light and noise whilst the system is active. This will be kept to a minimum.
Green Lane MSL will be operational from 05:00 Friday 27thJune.
Early July the Level Crossings Manager and his Line Manager will visit Green Lane to talk to users about the new crossing.